Library looking towards Librarian's office
August 18, 2009
Walking into library
August 18, 2009
Main administration building
August 18, 2009
Blue Arch Entrance
August 8, 2009
Kindergarten Farm Carpet - Includes a Red barn and cow sections
August 8, 2009
Admin building from playground view
August 8, 2009
View from the library
August 8, 2009
Middle School - lockers installed, floors finished, ready for furniture!
July 21, 2009
Cabinets installed
July 21, 2009
Admin scheduled for completion August 15th - windows in admin, sheet-rocking completed inside
July 21, 2009
finishing touches on Elementary floors
July 21, 2009
Compacting for sidewalks
July 21, 2009
Main & Elementary from field - preparing field for landscaping
June 30, 2009
Inside classroom. Cabinets being installed.
June 30, 2009
Admin building from field. Library on second floor
June 30, 2009
Colored glass light the hallways
June 30, 2009
Elementary view from street
June 30, 2009
Elementary with windows
June 9, 2009
View from 2nd story elementary classroom
June 9, 2009
Middle School - finish work nearly done!
June 9, 2009
Bathrooms tiled
June 9, 2009
Roads going in surrounding school
June 8, 2009
Looking North West. Windows in Middle AND Elementary School
June 8, 2009
Administration Building nearing completion of the block
May 27, 2009
View of campus - work on Elementary and Middle School inside finish work
May 27, 2009
Elementary and Admin. street view
May 7, 2009
Campus looking west
May 7, 2009
Middle School street side with windows
May 7, 2009
Admin. looking north.
May 7, 2009
Campus looking NE
May 7, 2009
Elementary - 2nd story nearly complete
April 26, 2009
Middle School facing street - Roof is Complete
April 26, 2009
Middle School facing field - framing inside, plumbing complete
April 26, 2009
Elementary Building 2nd Floor
April 14, 2009
View from Admin
April 10, 2009
Middle School Going Vertical (on left)
April 2, 2009
Moving to the second story on Elementary building
March 20, 2009
Walls Going up
March 7, 2009
Walls Going up
March 1, 2009
Footings Completed
February 15, 2009
Foundation Poured
January 29, 2009
Laying Water Retention Pipes
January 9, 2009
Preparing for Underground Water Retention
January 2, 2009
Closed on Land Purchase
December 8, 2008
Groundbreaking Ceremony
December 5, 2008